MONTHLY SITE UPDATE: MAY 2026
May sees continued progress on projects started in April, alongside important preparatory works for Phase 3 and developments at the cricket facilities. As work progresses across multiple areas of the site, teams remain focused on delivering key infrastructure and amenities for the growing community.
Road Past Vealeholme – Planning Update
The Sherford Consortium has taken the decision to postpone its application for a stopping-up order to close a section of highway known as 'Road Past Vealeholme'. Following careful consideration of feedback received, the Consortium will instead fulfil its Section 106 planning obligation through a financial contribution to Plymouth City Council for traffic management measures, and will apply for a temporary road closure in 2027 to enable essential gas and electricity infrastructure works. Full details are available here.
Sherford Road Traffic Calming Project
Work on the Sherford Road Traffic Calming project is progressing well and will continue through May. The project remains on schedule, with phased works taking place in accordance with the timeline shared with residents in April. Full information, plans and maps remain available at www.sherford.uk/planning
Cricket Facilities
Work is continuing on the cricket pitch, with landscaping activity currently preparing the crease for temporary summer use in 2026, and full opening for the 2027 cricket season. Associated works are also taking place on the culvert crossing and car park, which are needed before the public can use the space. Residents on Aries Lane may see this activity taking place from their windows.
Swale Improvements
Work continues on the swales - drainage channels designed to manage stormwater runoff - with installation of protective liners ongoing. This work supports the effective functioning of Sherford's drainage infrastructure.
Phase 3 Development
Preparations are underway for services installation further up into the site, with gas, electric and water infrastructure due to be installed in the coming weeks. Some road closures will be required to enable this work to take place safely. Full details will be communicated to affected residents nearer the time.
Phase 3 has also reached an important milestone, with the first residents due to move into the area imminently. This marks another significant step forward in Sherford's continued growth.
Please note: all information is correct at the time of publication, but timings may be subject to change.