MONTHLY UPDATE: AUGUST 2025
Estate completion works continue to advance in Phase 1B, which is now approximately 70% complete. This progress represents substantial improvements to the residential areas and supporting infrastructure that will benefit existing residents.
The primary school has successfully completed its final inspections, with all snagging and remedial works now finished, marking an important achievement for this vital community facility.
Infrastructure development maintains momentum with the culvert project between Phase 2D and Area 3AB progressing well. A notable milestone has been achieved with the installation of the bridge arc across the stream, a critical component of this essential drainage infrastructure.
Looking ahead, the upcoming weeks will see the commencement of implementing the first Key Spaces in Phase 2D. These important community areas will provide enhanced amenities and green spaces for residents to enjoy, further developing Sherford's character and community spaces.
*Please note: all information is correct at the time of being published but timings may be subject to change